Wednesday, July 27, 2011

Wednesday, 7-27-11

Slow day today, we have a traffic switch coming up this evening where we will be moving W.B. Arapahoe Road traffic onto new pavement. The new pavement will eventually become the final configuration of E.B. Arapahoe Road, however, at this point the pavement will serve to carry W.B. Arapahoe traffic. This new set up can be seen in the picture below.


Activities:

1. Hamon moving barrier from W.B. Arapahoe Road to new pavement at E.B. Arapahoe Road, West of the bridge.

2. Scott Contracting cleaning and sealing joints between sections of new pavement at E.B. Arapahoe Road, West of the bridge.

3. Scott Contracting drilling tie-bars in existing pavement for the new pavement that will be placed in the median of Parker Road, South of the bridge.

4. Colby Striping laying out new traffic pattern and painting lines on E.B. Arapahoe pavement and the Ring Road.

5. Hamon bringing in millings for new base course for the concrete pavement that will be poured to make up new S.B. Parker Road up to the bridge.

6. LV building embankment and shifting soil at various locations around the project.

7. Concrete Coring Company saw cutting small portions of existing concrete pavement at the project limits South of the bridge.