Tuesday, July 26, 2011

Tuesday, 7-26-11

Activities:

1. Hamon milling existing asphalt to match new concrete pavement on E.B. Arapahoe Road. This pavement will carry W.B. Arapahoe traffic temporarily while the new pavement for W.B. Arapahoe Road is being installed.

2. Scott Contracting saw cutting new pavement on E.B. Arapahoe, West of the bridge.

3. LV preparing ABC on S.B. Parker Road for new pavement, South of the bridge.

4. Hamon sorting and crushing recycled asphalt and concrete that has been removed throughout different phases of the project.