Tuesday, 8-2-11

Activities:

1. Absolute Quality pouring median covering material at the S.W. Ramp and along N.B. Parker Road.

2. Hamon milling the old W.B. Arapahoe Road.

3. Rocky Mountain Rodbusters setting rebar for the retaining wall that runs along S.B. Parker Road. North of the bridge.


Pictures of another project. These are pictures of the piles and pile caps. Another one is of the difference between the existing bridge and the new one being installed in its place. They were set to place girders here today, however, the concrete cylinders from the concrete used to pour the piles and pile cap has failed the crush test.