Friday, 7-29-11

Activities:

1. Scott Contracting pouring concrete for new median pavement on Parker Road, South of the bridge. Instead of using the forklift to extend a worker out to stab the dowels in the median, Scott brought a bridge instead.


2. Hamon milling what used to be W.B. Arapahoe Road, East of the bridge.