Tuesday, July 19, 2011

Tuesday, 7-19-11

Activities:

1. LV working embankments for South Parker Road, North & South of the bridge.

2. JDR working to resolve variouse erosion control issues throughout various areas of the project.

3. Urban Farmer spreading hay, throughout loop ramp and ring road areas.

4. Hamon preparing sub grade for last portion of new pavement of E.B. Arapahoe Road, West of the bridge.

5. 2:30 pm Proof Roll of the sub grade mentioned above.