Wednesday, August 10, 2011

Monday, 8-8-11

This will be my last post of the summer. It has been a learning experience working for the Colorado Department of Transportation. I have learned a lot and have gained many new contacts for the future.

 Activities:

1. LV Preparing sub-grade on old W.B. Arapahoe Road, East of the bridge.

2. Hamon milling old W.B. Arapahoe Road, West of the bridge.

3. Hamon/Rocky Mountain Rod Busters setting rebar for retaining wall for S.B. Parker Road at the N.W. corner of the bridge.



4. WL working on removing conduit lines across what will be the new N.W. off-ramp. The conduit boxes were located in the wrong places.


5. JDR working on erosion embankment behind the shopping center at the N.E. area of the project.

6. Hamon placing retaining wall forms for activity 3.

7. Scott Contracting setting string-line & pavement equipment for main line S.B. Parker Road pavement, South of the bridge.